This project covers fire doors for Hong Kong International Airport. The main contractor is BUCG-CCCL Joint Venture, with an approximate project value of HKD 10M. The airport's scale, numerous openings and stringent O&M standards demand large-batch supply, precise installation, high durability and close coordination with operational work windows.
Project Highlights
- Covers terminal public areas, back-of-house routes, plant rooms and key compartment openings
- Large-batch customisation and staged delivery to protect the overall programme
- Enhanced durability and reliable self-closing for intensive airport use
- Strict compliance with airport operational and airside/landside works controls
Scope of Work
- System detailing, opening checks and material submissions
- Batch fabrication, logistics and zoned installation
- Hardware commissioning, functional checks and protection
- Acceptance records, O&M training and handover support
On completion, the door systems provide stable performance and maintainability for this major transport hub.